How to build a client project timeline, counting business days
By SoloWOS teamPublished
IN SHORT
Build a client project timeline backwards from the deadline: list the deliverables, estimate each in business days, add client review time as its own step, and skip weekends and holidays. In 2026, Veterans Day, Thanksgiving and Christmas fall in the last two months. Put the timeline in the proposal so late feedback visibly moves the end date.
Prices and limits as of .
Key takeaways
- Count business days, not calendar days, and name the holidays you skip.
- Client review is a phase with its own days and owner, not a gap between your phases.
- A 29-business-day project starting Monday, November 2, 2026 ends Monday, December 14 once Veterans Day and Thanksgiving are skipped, two working days later than a weekdays-only count.
- Write the rule that moves the end date: each business day of late feedback moves launch by one business day.
A project timeline is a promise with dates on it, and the easiest promise to break is one made in calendar days. This guide shows how to build one in business days with client review written in as its own step. It is part of the time and projects hub; once the dates are agreed, a Kanban board for client projects tracks the daily work.
What you need first
- The deliverables, from the proposal or statement of work.
- An estimate per deliverable in hours, then converted to business days at the hours you really spend on this client per day.
- The number of review rounds and how many business days the client has for each.
- The holidays your client observes, and your own days off.
If you don't have hour estimates yet, estimating how long a project will take walks through task-by-task and three-point estimates. Convert hours to days honestly: if this client gets about 5 focused hours a day from you, a 20-hour build is 4 business days, not 2.5.
Steps to build the timeline
- Fix the end that matters: a launch date the client gave you, or the earliest start you can offer.
- List phases in order, each with its owner: you or the client.
- Give every phase a length in business days, including each client review round.
- Lay the phases on a calendar, skipping weekends and the holidays you listed.
- Mark the dates you need inputs from the client: content, access, feedback.
- Add one rule about delays, then put the table in the proposal.
Holidays matter because they land on both sides. US federal holidays are set by 5 U.S.C. 6103, and OPM's 2026 schedule lists 11 of them, including Veterans Day on Wednesday, November 11, Thanksgiving on Thursday, November 26 and Christmas on Friday, December 25. Banks follow the Federal Reserve's holiday calendar, so a milestone invoice due on a holiday won't be paid that day either. Many clients also take the Friday after Thanksgiving off even though it isn't a federal holiday; ask.
Worked example: a 6-week website project
| Phase | Owner | Business days | Dates |
|---|---|---|---|
| Discovery and content plan | You | 4 | Mon Nov 2 to Thu Nov 5 |
| Review round 1 (content plan) | Client | 3 | Fri Nov 6 to Tue Nov 10 |
| Design | You | 6 | Thu Nov 12 to Thu Nov 19 |
| Review round 2 (design) | Client | 3 | Fri Nov 20 to Tue Nov 24 |
| Build | You | 8 | Wed Nov 25 to Mon Dec 7 |
| Review round 3 (site on staging) | Client | 3 | Tue Dec 8 to Thu Dec 10 |
| Fixes and launch | You | 2 | Fri Dec 11 to Mon Dec 14 |
Counting weekdays only, the same 29 days would end on Thursday, December 10. Skipping the two holidays pushes launch to Monday, December 14. If the client is also off on Friday, November 27, launch moves to Tuesday, December 15. The business days calculator adds business days to a start date and lists the US federal holidays it skipped, so you can rebuild the table in a minute when a date changes.
WORKED EXAMPLE
What a late review does to this timeline
The client returns design feedback on Wednesday, November 25 instead of Tuesday, November 24: one business day late. Under the delay rule, every later phase moves one business day. Thanksgiving is skipped, so build runs Fri Nov 27 to Tue Dec 8, review round 3 is Wed Dec 9 to Fri Dec 11, and fixes and launch are Mon Dec 14 to Tue Dec 15.
Put the delay rule in writing
Timeline. The project starts on [start date] and is planned to launch on [launch date], counting business days (Monday to Friday, excluding [US federal holidays / list]). Client reviews. Each review round gives you [3] business days. Please send one consolidated list of feedback per round. Delays. If content, access or feedback arrives late, every later date moves by the same number of business days. Dates I miss on my side don't move your review time. Holidays. I will not be working on [your days off]. Dates above already account for them.
The clause does two jobs: it shows the client their part of the schedule, and it makes delays arithmetic instead of an argument. If you bill in stages, tie each payment to a phase end rather than a calendar date; milestone billing covers how.
Common mistakes
- Review time hidden inside your own phases, so a slow client looks like a slow freelancer.
- Calendar-day estimates ("two weeks for design") that quietly include a holiday.
- No date for inputs. "Client sends content" without a day is never late, so the launch is.
- Back-to-back projects with no slack. Leave at least a day between one client's launch and the next one's start.
In SoloWOS
Paste the timeline table into the proposal so the client accepts it with the price; with Proposals clients accept online and the accepted version is kept. Then, in Notes & Boards, add one task per phase with its end date as the due date on the client's board, so the board shows which phase is due this week. Notes & Boards doesn't draw Gantt charts; the table in the proposal is the timeline.
Questions
How do I make a simple project timeline?
List the phases in order, give each a length in business days, include each client review round as its own phase, and lay them on a calendar skipping weekends and holidays. A table with phase, owner, days and dates is enough for most freelance projects.
How many days should I give a client to review work?
Two to five business days per round is common. Shorter works for small deliverables like a page of copy; longer suits clients who need sign-off from several people. Whatever you choose, write it in the proposal and tie the end date to it.
Should my timeline count US federal holidays?
Count the days your client is actually closed. Most US companies close on New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving and Christmas; fewer close on Columbus Day or Veterans Day. Ask at kickoff and list the skipped days in the timeline.
What if the client misses a feedback deadline?
Apply the delay rule from the proposal: move every later date by the number of business days the feedback was late, and send the new dates in writing. Repeated delays may justify a pause clause or a restart fee, which belong in the contract.
Sources
Facts checked against these sources on October 18, 2026. Rules and amounts change, so confirm them at the source before you file or sign.
- OPM: Federal holidays (2026 schedule)
- 5 U.S.C. § 6103, Holidays
- Federal Reserve: Holidays observed by the Federal Reserve System
Last reviewed:
SoloWOS tools mentioned here
More on time and projects
- A 30-minute weekly review for freelancers (template)A copyable 30-minute weekly review checklist for freelancers: unbilled hours, overdue invoices, open proposals, next week's calendar and three priorities.
- Billable vs non-billable hours: what counts and how to price it inWhat counts as billable time, the non-billable tasks freelancers forget, and how to recover them through your hourly rate instead of the invoice.
- Client offboarding checklist: how to close a project properlyClose a client project properly: final invoice, file and password handoff, access removal, records to keep, a closing email and the review ask.
- How to estimate how long a project will takeEstimate project hours with task breakdowns and three-point (PERT) estimates. Worked example: a website estimated at 52 hours, checked against past jobs.
Run your client work from one account
14 days free, no card needed · Then Basic for $2/month.
Start your free trial